Questions emerge over Sh 500M part of Sh 1.4 billion KISIP projects in Homa Bay County as the program faces collapse

By Team

Concerns have emerged over Sh 500M part of the Sh 1.4 billion for the infrastructural developments by development partners for the Kenya Informal Settlements Improvement  Project (KISIP 2) in Homa Bay county.

 The first disbursement was part of the Sh 1.4 billion meant for infrastructural development, but no work has commenced even after the release of the funds.

Equally, questions have emerged over the award of the tender, with allegations that the first two candidates were not considered for the award, with the county government preferring to award the bidder who came third.

The irony is that the national government infrastructural projects that were earmarked for the Madaraka Day celebrations have been completed in a record time, while the donor-funded project that is being implemented by the county government is yet to take off, with the project term nearing the end.

And now the residents have expressed fear that the projects may stall following the failure of the contractor to commence work at the various sites in the county.

The Principal Secretary , State Department of Housing and Urban Development, has responded to the request for information and concerns raised by the Homa Bay-based civic organisation over the  Sh 1.4 billion Kenya Informal Settlements Improvement  Project (KISIP 2).

He said the infrastructure upgrade implementation has not commenced. 

The project, which is a five-year program,  became effective in March  2021 and is expected to close in July 2025 for International Development Agency (IDA)financing and in December 2028 for the Agence Française de Développement (AFD) financing.

Interface Community Desk had written to the PS Charles Hinga seeking to know the  total length  of roads  being upgraded  or constructed under  KISIP 2, detailed dimensions and specifications for the roads, including  carriageways, footpaths and drainage system.

 Design plans and layout for infrastructure improvement, progress reports, tenders or contracts, and detailed bills for quantities for the roads.

“From our monitoring of the ongoing KISIP 2 road projects, we have serious concerns that the works currently being done do not conform to required standards.

We strongly urge your office to provide clarity on whether the roads currently being constructed meet the approved standards under KISIP 2  and whether any modifications are planned to correct these concerns,” wrote Evans Oloo Gor, chairperson of the organisation.

The PS, in his response to the status of the project, wrote, “On the infrastructure upgrade, implementation has not commenced. 

The project is still in the process of recruiting an implementing partner to support community-led implementation of labour-intensive community works (LICW) in selected informal settlements.

The services will include support in designing the agreed-upon activities and supervision of work and workers.

This will entail engaging the community and other stakeholders in co-designing, drawing, bill of quantities, preparation of schedules of materials, tools, equipment, labour, as well as the supervision of work and workers.”

Hinga said in Homa Bay county,  the interventions of KISIP 2 under sub-component 1.2 covers Makongeni, Shauri Yako, Sofia, a thousand streets, Nyandiwa and Rusinga old town settlements.

“ The proposed interventions for the large works entailed, construction of a total of 9.7km and 2.3 km of 9km and 6km wide corridor roads respectively, and roadside drainage works as well as foot paths in all six settlements.

Construction of a box culvert in Makongeni settlement, construction of 2.4 km wide by 1.3m deep by 1.08km long along storm water in Shauri Yako and construction of 0.922km long roadside drains along tarmacked roads in Shauri Yako and construction of 2m wide by 2m deep by 1.65km long storm water drainage in Nyandiwa.

Construction of 30 m high security mast in Shauri Yako, three in number, Sofia, Makongeni, A Thousand Street, one each, Nyandiwa 2.

Construction of  436 solar-powered street lighting in selected roads in all six settlements, construction of ablution blocks in Shauri Yako (2), Rusinga old town (1) and construction of elevated tanks of capacity 100 mm2 in Shauri Yako and Rusinga old town.

Construction of vending platforms in Shari Yako and Nyandiwa, and landscaping and greening of children ‘s park Shauri Yako,” he wrote.

Hinga said the contract for large works funded by IDA had been awarded to MS Richpam Company Limited in a joint venture with Ms. Sajucy Company Limited at a sum of Sh 1,407,104,554.44.

The works commenced in June 2024, with the current estimated progress standing at 36 per cent against time elapsed of 60 per cent.

Hinga said the survey process has been concluded with LP&LUDP being approved and the RIMS amended.

The project is undertaking further verification of the lists of beneficiaries to allow for the preparation of ownership documents.

The County spokesperson and Chief Officer of Communication, Ms. Atieno Otieno, did not respond to our text messages.

Hot this week

THE POTENTIAL OF MIGORI SUGAR-BELT REGION UNTAPPED

By Billy Mijungu The sugar belt region of Migori County...

SIFUNA, KALONZO, MATIANG’I, ORENGO, BABU, WAMALWA, MUTURI, NDINDI, UHURU AND GACHAGUA — THIS IS THE LIST

By Billy Mijungu With their respective support bases, we are...

The “reincarnate” Siaya Governor, Orengo, a political thorn in Kenya

By Anderson Ojwang From public demands and rumours over his...

Heads Roll as House Adopts Ad-Hoc Committee Report on Own-Source Revenue

By Kisumu County Assembly Press The House yesterday (Wednesday, 3rd...

Mama Ida to Raila’s bodyguard Ogeta: I thank God, Gor Mahia finally brought you here

By Anderson Ojwang A day that was meant to celebrate...

Topics

THE POTENTIAL OF MIGORI SUGAR-BELT REGION UNTAPPED

By Billy Mijungu The sugar belt region of Migori County...

The “reincarnate” Siaya Governor, Orengo, a political thorn in Kenya

By Anderson Ojwang From public demands and rumours over his...

Heads Roll as House Adopts Ad-Hoc Committee Report on Own-Source Revenue

By Kisumu County Assembly Press The House yesterday (Wednesday, 3rd...

Kansai Plascon Rewards Gor Mahia, Extends Three-Year Ksh30 Million New Deal

By PHILLIP ORWA 22-time Football Kenya Federation Premier League title...

Cynthia Muge Unveils 11-Point Plan to Fix Nandi’s Road Network

By Remmy Butia Gubernatorial hopeful Cynthia Muge has rolled out...

Learning resumes at Ambira Boys after students return following strike

By Hope Barbra Learning has resumed at Ambira Boys High...

Related Articles

Popular Categories